QUESTION 21
Your organization uses Project Server 2013. For security reasons, only individuals inside your
organization have access to Project Web App (PWA). You want to keep track of progress made by
a third-party vendor. The vendor will email task progress to the resource manager. The resource
manager will be responsible for reporting vendor progress back to the project manager in PWA.
You need to enable this functionality. You add the vendor as a resource in Project Server. What
should you do next?
-
Assign the resource manager as the Status Manager.
-
Assign the project manager as the Assignment Owner.
-
Assign the resource manager as the Assignment Owner.
-
Assign the administrator as the Status Manager.
Correct Answer: C
QUESTION 22
You are a project manager in an organization that uses Project Server 2013. Project team
members submit updates to tasks through Project Web App (PWA). A project team member clicks
Remove Task, and you approve it. You apply this change to the project. The team member
indicates that they only want to hide the task from that particular view, not remove the task
permanently. You need to ensure the task is returned to the Tasks page so it can be properly
hidden. What should you do?
-
Mark the task as active and publish the project.
-
Tell the team member to choose Add Row and click Add Team Task.
-
Tell the team member to modify the filter to show incomplete tasks.
-
Assign the team member to the task and publish the project.
Correct Answer: D
QUESTION 23
You are a project manager for an organization that uses Project Server 2013. As part of a regular
project review, you notice that several tasks of one of your projects that should be finished are
outdated. You need to update those tasks with the exact percent complete as of today. Which
three steps should you perform? (Each correct answer presents part of the solution. Choose
three.)
-
Open the project for editing in Project Web App (PWA).
-
Type today’s date in the Actual Start field for each outdated task.
-
Open the project for editing in Project Professional 2013.
-
Type today’s date in the field Update work as complete through.
-
Click the Update Project button.
Correct Answer: ADE
QUESTION 24
Your organization uses Project Server 2013. You are the project manager of a schedule. Team
Members send you emails with their percentage complete on their assignments. Your
organization only uses the following two percentages for tracking tasks:
-
50% for tasks that are started
-
100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA. What are two possible ways to achieve this goal? (Each
correct answer presents a complete solution. Choose two.)
-
In PWA, open the Tasks screen, select the task(s), and enter 50% or 100% in the % Complete
field.
-
In PWA, open Project Center. Edit the Project, and enter either 50% or 100% in the %
Complete field of each task, as needed.
-
In PWA, open Project Center. Edit the Project, select the task(s), and select the 50% or 100%
button in the ribbon.
-
In PWA, open the Microsoft SharePoint site for the schedule, select the task(s), and update
the % Complete field to either 50% or 100%.
Correct Answer: BC
QUESTION 25
As a team member, you submit your timesheet for approval in Project Server 2013. After sending
the timesheet to the timesheet manager, you realize you forgot to include some work. You need
to ensure that the work is added to your timesheet. What are two possible ways to achieve this
goal? (Each correct answer presents a complete solution. Choose two.)
-
Make an adjusting entry on your next timesheet and then submit that one.
-
Re-open it immediately. Make your changes and re-send it.
-
Recall the timesheet from the Manage Timesheets page. Make your changes and resend it.
-
Ask your timesheet manager to reject your timesheet. Make your changes and resend it.
Correct Answer: CD
QUESTION 26
You are a project manager for an organization that uses Project Server 2013. Your team members
update their task status. You need to see how these updates impact your project before you
approve the tasks. What should you do?
-
Go to the Approvals page, select the tasks, and preview updates to analyze the impact in
your Project.
-
Open Project Professional 2013, select the tasks, and preview updates to analyze the impact
in your Project.
-
Go to the Status Report page, select the tasks, and preview updates to analyze the impact in
your Project.
-
Go to the Project Schedule page, select the tasks, and preview updates to analyze the impact
in your Project.
Correct Answer: A
QUESTION 27
You are a project manager who has standard permissions, and your organization uses Project Server 2013. Some of your resources consistently update their assignments correctly. You want to accept their future updates without review. You need to begin accepting their updates without review by using the least amount of effort possible. What should you do?
-
Set up a rule in the Approval Center to automatically accept ail updates, specifying the
resources by name, for all projects.
-
Set up a VBA macro to automatically accept all updates, specifying the resources by name,
for all projects.
-
Set up a Project Server 2013 workflow by using Microsoft SharePoint Designer to
automatically accept all updates, specifying the resources by name, for all projects.
-
Set up a timesheet event handler in the Project Server Settings to automatically accept all
updates, specifying the resources by name, for all projects.
Correct Answer: A
QUESTION 28
You are a project manager for an organization that uses Project Server 2013. You have the default
Project Server security permissions and can modify your Project Site. Your project schedule has a
Project Site, which includes a Document Library that contains some standard documents and a
calendar view used only for project meetings. You need a separate calendar view to track team
members’ vacation dates. What should you do?
-
In the Project Server 2013 Project Site, use the Add Lists, Libraries, or Apps button and create
a new Calendar.
-
Ask the Project Server administrator to elevate your permissions and give you the ability to
create a new calendar.
-
Ask the Project Server administrator to create your desired Calendar view and add it to the
default Project Site.
-
In Project Professional 2013, create a new Calendar view for the schedule. The next time you
publish the schedule, the new Calendar view will be available in the Project Site.
Correct Answer: A
QUESTION 29
You are a program manager in the Project Management Office (PMO) of an organization that has
Project Server 2013. You plan to have a weekly project meeting review with all the project
managers, and one of the topics that you will cover is the status of all active Issues. Your need to
create a report that displays the following information:
-
Name, Status, Priority, and Resolution of all Issues
-
Name, Owner, and Start and Finish date of all projects
What should you do?
-
Create a Microsoft Excel Services report that pulls information from the Issues cube.
-
Create a Microsoft Excel Services report that pulls information from the Microsoft SharePoint
Configuration Database.
-
Create a Microsoft Excel Services report that pulls information from the Microsoft SharePoint
Content Database.
-
Create a Microsoft Excel Services report that pulls information from the Project Server 2013
database.
Correct Answer: D
QUESTION 30
You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013. You review your organization’s issue management process. You need to
implement a new issue management process that meets the following requirements:
-
All issues for future projects need to be associated with a source.
-
Source values are either Internal or External.
What should you do?
-
Instruct the users to attach a text file with the source information every time they create a
new issue.
-
Instruct the users to write the information about the source into the description field every
time they create a new issue.
-
Add a new enterprise custom field named Source with an associated lookup table which
contains the values Internal and External. Make this field required. Save the Project Site as a
template for new Project Sites.
-
Go to a Project Site, and customize the issue list by including a new column to allow a value
from Internal or External options to be chosen. Make this field required. Save the Project Site
as a template for new Project Sites.
Correct Answer: D
Instant Access to Download Latest Complete Collection of Microsoft Specialist Certification 74-344 Real Exam
Try Microsoft Specialist Certification 74-344 Free Demo
70-410 Dumps VCE PDF
70-411 Dumps VCE PDF
70-412 Dumps VCE PDF
70-413 Dumps VCE PDF
70-414 Dumps VCE PDF
70-417 Dumps VCE PDF
70-461 Dumps VCE PDF
70-462 Dumps VCE PDF
70-463 Dumps VCE PDF
70-464 Dumps VCE PDF
70-465 Dumps VCE PDF
70-480 Dumps VCE PDF
70-483 Dumps VCE PDF
70-486 Dumps VCE PDF
70-487 Dumps VCE PDF