QUESTION 61
You are a project manager who uses Project Professional 2013. Your organization has been
working with a new status report model for the last month. This new status report is created
through the Built-in Dashboards and Reports in Project Professional 2013. The standard Project
Professional 2013 report views named Late Tasks and Milestone Report already have all the
information required for the new model. You are assigned to consolidate the information from
these two reports into a dashboard view named Status Report Model. Your organization wants to
keep the same format, colors, and layout. You need to implement this solution. What should you
do?
-
Use the Organizer to merge the reports.
-
Select all components on each view, and copy and paste directly to a new dashboard report.
-
Use the Burndown dashboard report to view this information.
-
Use the Work Overview dashboard to view the data.
Correct Answer: B
QUESTION 62
You are a project manager who uses Project Professional 2013. Your organization migrates all
project plans from Microsoft Excel to Project Professional 2013. One of the directors of the
company has several years of experience using Excel Pivot Tables to analyze and make decisions
about projects. You need to enable project managers to view relevant project information in
Excel Pivot Tables. What should you do?
-
Create a Report view by using the new Built-in Dashboards and Reports feature and export to
Excel.
-
Download and install the Microsoft Project to Pivot Table Tool and generate a new Excel Pivot
Table by selecting the current project.
-
Use the Excel Data From Other Sources feature to access your project file.
-
Create a report by using the Visual Reports feature. Select Microsoft Excel and choose
relevant data to view in the report.
Correct Answer: D
QUESTION 63
Your company uses Project Professional 2013. An organization with project managers of varying
expertise wants a simple, standard view that displays overall project status. You need an
out-of-box function that provides the ability to assess current, baseline, and actual work for the
project. Which view should you use?
-
Project Overview dashboard
-
Resource Allocation view
-
Work Overview dashboard
-
Relationship Diagram view
Correct Answer: C
QUESTION 64
You are an independent project manager who uses Project Professional 2013. You work on
multiple projects for different customers and use only one project to manage their tasks. You
invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you
create a custom field called Not Invoiced. Without losing the original project tasks’ sort order, and
without hiding any information, you need to see all tasks which have not been invoiced. You
create a custom filter based on the Not Invoiced custom field. What should you do next?
-
Apply the custom filter.
-
Export to Microsoft Excel using the custom filter.
-
Apply the custom filter and select the Highlight option
-
Use the filter in the Group By function.
Correct Answer: C
QUESTION 65
You are a project manager, and you use Project 2013 for a large construction project. You create
the work breakdown structure (WBS) and plan to add the following resources for your project:
concrete, construction supplies, and airline tickets. You need to add these resources to your
schedule. Which two resource types should be created for these resource examples? (Each
correct answer presents part of the solution. Choose two.)
-
Add Generic Resources.
-
Add Cost Resources.
-
Add Work Resources.
-
Add Material Resources.
Correct Answer: BD
QUESTION 66
You are a project manager who uses Project Professional 2013. You work on a software
development project, and the Project Management Office (PMO) requires you to enter project
costs associated with all work completed on your project. You receive invoices for 55,000 for
software licenses and $150 for supplies. Software licensing costs are associated with Task A:
Obtain Software License. Supply costs are associated with Task H: Project Management
Administration. You need to enter the costs into your project schedule. Which two steps should
you perform? (Each correct answer presents part of the solution. Choose two.)
-
Create a cost resource for Supplies and Software License.
-
Create a material resource for Supplies and Software License.
-
Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A, and enter the actual costs using the Task Usage – Cost table for both Task H and A
-
Assign the Supply material resource to Task H, assign the Software License material resource
to Task A, and enter the actual costs using the Task Usage – Cost table for both Task H and A
Correct Answer: AC
QUESTION 67
You are a project manager who uses Project Standard 2013. You manage a software development
project and have acquired two additional resources to assist in the completion of tasks that are
on the critical path. Both resources are also assigned to participate in other projects. Resource1 is
available 50% and Resource2 is available 75%. You need to add the resources with their
availability to the project schedule and make any allocation problems visible. What should you
do?
-
Assign the two resources to the tasks with the following units:
Resource1 = 50%, Resource2 = 75%.
-
Select the Resource Sheet and change Max Units to the following:
Resource1 = 50%, Resource2 = 25%.
-
Select the Resource Sheet and change Max Units to the following:
Resource1 = 50%, Resource2 = 75%.
-
Assign the two resources to the tasks with the following units:
Resource1 = 50%, Resource2 = 25%.
Correct Answer: C
QUESTION 68
Drag Drop
You are a senior project manager in a software development company. You manage your projects
with Project Professional 2013. The development team is behind schedule due to a problem
found in the architectural design of the database. The lead architect estimates that redesigning
the database will take approximately 30 hours. You create a new manual task and assign it to the
lead architect. However, the task has not been scheduled. You need to easily see a time phased
view of all tasks for the lead architect in order to schedule the task for completion. Which three
actions should you perform in sequence?
To answer, move the appropriate three actions from the list of actions to the answer area and
arrange them in the correct order.
Select and Place:
Correct Answer:
QUESTION 69
You work as a project manager for a construction company that uses Project Professional 2013.
You have created your work breakdown structure (WBS) and are adding resources to your tasks.
However, one of your tasks requires multiple resources. You have the name of the project’s lead
support individual, and you have been provided with the equivalent of three full-time support
resources. These three resources are not named individuals but are part of a group. The actual
individuals from this group will change based on coverage schedules. The resources have the
following cost structures:
-
The lead is billed out at S175/hour.
-
The group resources are billed out at $140/hour.
You need to add these resources to the schedule and track your project costs. Which two actions
should you perform? (Each correct answer presents part of the solution. Choose two.)
-
Add the named resource to the task with an allocation of 100% and a standard rate of
$175/hour.
-
Add the named resource to the task with an allocation of 400% and a standard rate of
$157.50/hour.
-
Add the group resource to the task with an allocation of 300% and a standard rate of
$140/hour.
-
Add the group resource to the task with an allocation of 100% and a standard rate of
$l40/hour.
Correct Answer: AC
QUESTION 70
You are a project manager for a large telecommunications company that uses Project Professional
2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the
entire project and not for an individual task. You need to add the fixed cost of S 150,000 to your
schedule and spread it across the duration of the project. What should you do?
-
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
Task 0. Change Fixed Cost Accrual to Start.
-
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
Task 0. Change Fixed Cost Accrual to Prorated.
-
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
Task 0. Change Fixed Cost Accrual to End.
-
In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
Task 1. Change Fixed Cost Accrual to Start.
Correct Answer: B
Instant Access to Download Latest Complete Collection of Microsoft Specialist Certification 74-343 Real Exam
Try Microsoft Specialist Certification 74-343 Free Demo
70-410 Dumps VCE PDF
70-411 Dumps VCE PDF
70-412 Dumps VCE PDF
70-413 Dumps VCE PDF
70-414 Dumps VCE PDF
70-417 Dumps VCE PDF
70-461 Dumps VCE PDF
70-462 Dumps VCE PDF
70-463 Dumps VCE PDF
70-464 Dumps VCE PDF
70-465 Dumps VCE PDF
70-480 Dumps VCE PDF
70-483 Dumps VCE PDF
70-486 Dumps VCE PDF
70-487 Dumps VCE PDF